Mn/DOT awarded Stonebrooke Engineering TH 60 Phase 1 and 2 Reconstruction in Worthington, MN
Stonebrooke Engineering was recently awarded final design of Phase 1 of the TH 60 Reconstruction project, and preliminary design of Phase 2. The first phase is a 6 mile road realignment / reconstruction beginning south of Worthington, and running north along TH 60. The existing 2-lane rural section is being redesigned into a 4-lane divided rural section. The second phase connects to Phase 1, and continues 2.5 miles north into the City of Worthington. The proposed 4-lane divided rural section will transition to a 4-lane divided urban section as the roadway enters the City. This project includes the design of a multi-lane roundabout at the intersection of TH 60 and CSAH 35.

Early concept geometrics for roundabout at TH 60 and CSAH 35